Highway 32 Project (Construction Updates)

 

05/24/2018

  • Due to the rain on Monday May 21st, the FULL CLOSURE of Highway 32 at 5 Mile Road for paving, was moved to Tuesday May 22.
  • For the remainder of this week, the contractor will be performing landscaping and restoration work on the disturbed areas as much as possible.
  • Unfortunately due to the rain that has been experienced this month, the project over the last week and a half and the remaining work to be done has progressed slower than originally proposed.
  • After a meeting with the contractor on Tuesday May 22nd, the restoration work will extend into next week.
  • On Tuesday May 29th and Wednesday May 30th, the contractor will be performing the remaining restoration, cleanup of materials, removal of equipment, etc. throughout the project area.
  • On Thursday May 31st, the traffic control contractor is scheduled to be out to remove all of the traffic control and OPEN Highway 32 to all traffic.

All of the remaining work is highly Weather dependent and the schedule may be subject to change.

Once the work above is completed, this will end the Village’s work for relocating utilities on Highway 32 in preparation for the DOT project. 

Remaining work under this contract, which is near the area, but not effected by the DOT project is:

  • a sanitary sewer relay across Highway 31 near Kingdom Court,
  • a sanitary sewer lateral repair across the majority of Highway 31, North of 4 Mile Road,
  • and a watermain relay on 6 Mile Road East of Highway 32.

The Highway 31 work will require a FULL CLOSURE of Highway 31.  (Approximately 2 weeks)

The 6 Mile Road work will require a FULL CLOSURE of 6 Mile Road East of Highway 32.  (Approximately 2 weeks)

The remaining work on Highway 31 and 6 Mile Road has been projected to start around the middle of July

 

Please remember that our contractor needs to have a safe work environment.

Please drive with care and slow down when passing workers and equipment.

 


 05/18/2018

  • Monday May 21st there will be a FULL CLOSURE of Highway 32 at 5 Mile Road. This closure will be for approximately 2 HOURS starting at 7:00am and ending at approximately 9:00am.

  • This Full Closure is for the asphalt contractor to prep and pave the sanitary trench that was placed across Highway 32 in this location

  •  Also on Monday, the contractor will be paving the crossing of Highway 32 for the watermain at Meadow Drive. These asphalt patches will be done under local traffic only.

  • All the remaining construction trenches on the project will be paved on Monday as well.

  • On Monday, Tuesday, and Wednesday, the contractor will be performing landscaping work to restore the disturbed areas.

  • On Wednesday and Thursday, the contractor will be performing various cleanup of materials, equipment, etc throughout the project area.

  • On Friday May 25th, the traffic control contractor should be out to remove all of the traffic control and OPEN Highway 32 to all traffic.

 All of this work is Weather dependent and schedule is subject to change.

This will end the Village’s work on Highway 32.

Remaining work under this contract is

  • a sanitary relay on Highway 31 near Kingdom Court,

  • a sanitary lateral repair on Highway 31 North of 4 Mile Road

  • a watermain relay on 6 Mile Road East of Highway 32.

The Highway 31 work will require a FULL CLOSURE of Highway 31.  (Approximately 1.5 weeks)

The 6 Mile Road work will require a FULL CLOSURE of 6 Mile Road East of Highway 32.  (Approximately 2 weeks)

The dates for this work are being worked out with the contractor.


05/11/2018

Due to a request from one of the businesses and the weather, the Full Closure of Meadow Drive scheduled for today was changed to Monday.

  • On Monday May 14th, there will be a FULL CLOSURE of Meadow Drive at Highway 32.

  • The Contractor will be open cutting the water main in Meadow Drive in this location.

  • This is proposed as a 1 day Full Closure of Meadow Drive ONLY.

  • All Businesses on Highway 32 will have access from the North, South, East and limited from the West.

  • All Businesses on Highway 32 will be accessible from the North, South, West (5 Mile Road, Matthew Drive, Harvest Lane, and Tabor Road), and East (5 Mile Road).

On Tuesday May 15th, there will be a FULL CLOSURE of Tabor Road at Highway 32.

  • The Contractor will be offsetting the watermain at Tabor Road.

  • There also is some minor insulating of the watermain that will be done near the intersection.

  • This is proposed as a 1 day Full Closure of Tabor Road ONLY.

  • All Businesses on Highway 32 will have access from the North, South, East and limited from the West.

  • All Businesses on Highway 32 will be accessible from the North, South, West (5 Mile Road, Matthew Drive, Harvest Lane, and Meadow Drive), and East (5 Mile Road).

The Tentative schedule for the remainder of the week will not include any Full Closures

  • 5/16 – Matthew Drive Insulate watermain (at Highway 32), Harvest Lane Insulate watermain (at Highway 32), Water Lateral Work

  • 5/17 – Edgar Terrace Insulate watermain (at Highway 32), Water Lateral Work

  • 5/18 – Water Lateral Work.

 All Businesses on Highway 32 will have access from all directions.


Tentative Schedule for the remainder for the Highway 32 Work

  • 5/18 – Pave and Clean Up

  • 5/21 – Clean up

  • 5/22 – Open Road

 

All of the work is Weather dependent and schedule is subject to change.

There is additional work required on Highway 31 that will require a several day closure.

Those dates have not been determined yet.

There also is additional work required on 6 Mile Road that will require a possible 1 week closure.

Those dates have not been determined yet.

 


 

 05/04/2018

  • Starting on Monday, May 7th through Wednesday, May 9th there will be a FULL CLOSURE of Highway 32 at 5 Mile Road.

  • The Contractor will be relaying the Sanitary Sewer across all 4 lanes of Highway 32.

  • Due to having an open trench for this portion of the project there will NOT be traffic allowed through the work zone.

  • See the attachment for the area of the Closure on Highway 32 at 5 Mile Road (found at bottom of page) 

During this Full Closure…

  • All Businesses on Highway 32 between 5 Mile Road and 6 Mile Road will NOT have access from the South (South of 5 Mile Road) or from the East (5 Mile Road from Middle Road).

  • Businesses will only be accessible from the North (6 Mile Road) or West (5 Mile Road, Matthew Drive, Harvest Lane, Tabor Road, and Meadow Drive).

Pending finishing the Construction on Monday, Tuesday, and Wednesday…

  • Tentative for Thursday May 10th, there will be a FULL CLOSURE of Highway 32 at Meadow Drive.

  • The Contractor will be open cutting the watermain in Highway 32 in this location.

  • Due to having an open trench for this work, there will NOT be traffic allowed through the work zone.

During this Full Closure…

  • All Businesses on Highway 32 South of Meadow Drive, will NOT have access from the North (6 Mile Road) or from the West on Meadow Drive.

  • Businesses on Highway 32 South of Meadows Drive will only be accessible from the South, West (5 Mile Road, Matthew Drive, Harvest Lane, and Tabor Road), and East (5 Mile Road).

  • All Businesses on Highway 32 North of Meadow Drive, will NOT have access from the South or West.

  • Businesses on Highway 32 North of Meadow Drive will only be accessible from the North (6 Mile Road).

Pending the Weather and Construction above…

  • Tentative for Friday May 11th, there will be a FULL CLOSURE of Meadow Drive at Highway 32.

  • The Contractor will be open cutting the watermain in Meadow Drive in this location.

  • All Businesses on Highway 32 will have access from the North, South, East and limited from the West.

  • All Businesses on Highway 32 will be accessible from the North, South, West (5 Mile Road, Matthew Drive, Harvest Lane, and Tabor Road), and East (5 Mile Road).

Tentative schedule for the remainder of the project

  • 5/14 – Tabor Road (at Highway 32) Closed

  • 5/15 – Matthew Drive (at Highway 32) and Harvest Lane (at Highway 32) Closed

  • 5/16 – Edgar Terrace (at Highway 32) Closed

  • 5/17 – 5 Mile Road West (at Highway 32) Closed

  • 5/18 – Pave and Clean Up

  • 5/21 – Clean up

  • 5/22 – Open Road

 As for right now, the tentative schedule is to OPEN Highway 32 back up to all Traffic on May 22.

Click here for May 7 to May 9 Closure Map

Click here for Traffic Routing 4/30 - 5/16 Map 


05/03/2018

  • The Contractor had been working under a Full Closure at 5 Mile Road today.  This was required due to needing an open trench that will need to go across all 4 lanes.

  • Due to an unforeseen condition and eminent rain in the forecast for Thursday, it had been determined that the Full Closure at 5 Mile Road will end this evening.

  • The open trench area in the North bound lanes will be closed back up, made safe, and passable to allow access to the residences and the Businesses from Highway 32 from the South.

  • For the remainder of this week 5/2 to 5/6 there will not be a Full Closure on Highway 32 between 6 Mile Road and 5 Mile Road.

  • This means that there will be access to Highway 32 Businesses between 6 Mile Road and 5 Mile Road from all directions.

  • The Full Closure at 5 Mile Road has been postponed to at least Monday 5/7/2018.

  • For the remainder of the week the contractor will be working on various manhole rehabilitations in the shoulder and in the road ditch area of Highway 32.

  • This again work will not require a Full Closure and will allow access to the residences and Businesses from all directions.


04/27/2018

  • Beginning Monday, April 30th through approximately May 16th Hwy 32 will be CLOSED from 300’ South of 5 Mile Rd to 6 Mile Rd.

  • Water and Sewer will commence near 5 Mile Road and continue North to 6 Mile Road.

  • All Truck traffic will need to follow the posted detour.  Local Traffic Only - No Thru Traffic.

  • Local Traffic is Only the residents that live within in the Closed Zone and traffic that is going to the businesses within the Closed Zone.For the week of April 30th to May 4th Sanitary Sewer work will commence near 5 Mile Road. 

  • Local traffic is recommended to enter the Closed Zone from the West and North.​

Click here to see the attached Map for the detour route during this closure. 